OREANDA-NEWS. March 11, 2013. A letter of gratitude from director of Municipal Enterprise of Schelkovo District “Schelkovo Electric Grids” S.A. Belousov came to the address of Director General of JSC “MOESK” Pyotr Sinyutin. The letter specifies a high level of the organization and quality of the works, carried out by the power engineers of MOESK on the grid connection implementation of a large facility of city Schelkovo – hypermarket “Kastorama”, an operational switching on of new feeders from SS 705 “Zhegalovo”.

Such contracts on the grid connections implementation of the power receivers of the socially significant facilities of the Company are under a special control in the grid connection Department of Moscow Region. Execution of one of them, concluded in March of 2011, consisted in the grid connection implementation of the power receivers of Schelkovo hypermarket “Kastorama” and was meant for two years. On part of a grid organization the project stipulated carrying out of a complex of the works at SS 730 “Grebnevo” of Schelkovo DZ (distribution zone) of the Eastern Electric Grids.

Area of hypermarket “Kastorama” is 9,700 sq.m. To implement timely the project, JSC “MOESK” created a working group, the membership of which became the employees of the unit for the grid connection in Moscow Region, those from the capital construction division of the Company and its branch “Eastern Electric Grids”, in the responsibility area whereof the substation is located. Regular visits of the employees of the unit for the grid connection in Moscow Region were made to the construction site of the electric grid facilities.

Works on switching on of feeder #35 at SS 730 “Grebnevo” were completed by the joint efforts of the Eastern branch’s power engineers and specialists of MOESK, long before a term expiry, determined by the contract. As a result the facility was supplied with voltage in summer of 2012.

Complex of the works, fulfilled by the power engineers at SS 705 “Zhegalovo” in the course of execution of one more contract, was composed of the arrangements to switch on new feeders from SS 705 “Zhegalovo” and to transfer the grids from the voltage 6 kV to the voltage of 10 kV.

Obligations fulfillment on part of the grid organization to the full extent and within the established terms has made it possible to provide a reliability and guarantees of a high quality of the power supply of the housing block and infrastructure of military unit 45807 “Zagoryanskiy”, located in settlement Zagoryanskiy of Schelkovo region.