OREANDA-NEWS. LLC "STROYGAZMONAZH" successfully completed hydrotests within Sheksninskaya CS that is in Gryazovets-Vyborg section of Sheksninsk District Vologda Region within Nord Stream second string.

Hydrotests are carried out for checking strength and structural integrity of process pipelines and equipment.

At the current moment the works for handing over the installed equipment to the stage of set up are continued within station. Commissioning of the facility is scheduled for II quarter, 2013. LLC "Gazprom invest" plays the role of the Customer. Aggregate capacity of the compressor station is 64 MW.

LLC "SGM" performs construction of six compressor stations within the second string of Gryazovets-Vyborg gas trunkline. In 2012 were commissioned such compressor stations as Gryazovetskaya CS, Elizavetinskaya CS and Babaevskaya CS.