OREANDA-NEWS. In accordance with the supplementary agreements to the state contract signed by OJSC Mostotrest and the Moscow City Construction Department, for construction and overhaul of a complex of transport infrastructure facilities in the west of Moscow, in particular the development of transport links with the Skolkovo Innovation Centre, Mostotrest is currently working on the following projects:

Southern section of the North-West chord (from Leningradskoye Avenue with an exit onto Mnevniki St. via Narodnogo Opolchenia St.), due to be completed by December 2014 (including operational set up). Project price: RUB 9.76 billion (including VAT);

Road section from the intersection of the Garden Ring with Novy Arbat St. to the intersection of Mozhaiskoye Avenue with the Moscow Ring Road, due to be completed by January 2015 (including operational set up). Project price: RUB 13.28 billion (including VAT);

Reconstruction of the Mozhaisky overpass, due to be completed by December 2014 (including operational set up). Project price: RUB 1.59 billion (including VAT);

Road junction at the intersection of Mozhaiskoye Avenue with the Moscow Ring Road, due to be completed by December 2014. Project price: RUB 7.62 billion (including VAT).

A number of additional agreements are expected to be signed as part of the state contract, including agreements on construction work to be performed on the following sites in the southern section of the North-West chord:

Skolkovskoye Highway up to the Moscow Ring Road; Mozhaiskoye Highway - The Moscow Ring Road with an exit onto Ryabinovaya Street, including Vyazemskaya Street and Vitebskaya Street;

General Dorokhova Street from Aminyevskoye Highway to the Moscow Ring Road;

Ryabinovaya Street.

The full complex of works is planned for completion in December 2016.