OREANDA-NEWS. In 2014, as part of the implementation of the re-equipment and reconstruction program, JSC "Belgorod Heat Grid Company" (100% subsidiary of JSC "Quadra - Power Generation") built 4.6 km of heating grids to the consumers newly connected to the centralized heating system. Over RUR 50 mn were spent on this purpose.

"In 2014, we were actively engaged in grid connection of new consumers to the central heating system. This is consistent with the current Russian laws and grid connection contracts. We are laying heating grids to residential buildings and infrastructure facilities under construction. We try to do the work quickly and efficiently. In 2014, 18 new consumers were connected in the cities of Belgorod and Gubkin, including houses, social facilities and others. The connected load of the company increased by 25 Gcal/h," Victor Fedyukov, director of JSC "Belgorod Heat Grid Company" said.

The number of connected facilities included nine new houses in Svyato-Troitsky Boulevard, Narodny Boulevard; Kostyukova, Sadovaya, Gubkina, Gorkogo Streets, Mikhailovskoe Highway and 60 Let Oktyabrya Street in Belgorod. Heat supply grids were built to the facilities of the regional center in Sportivnaya, Korolyova, Svobodnaya Streets. The Recreation Center was connected in the village Nikanorovka of the Gubkin urban district; the kindergarten "Svetlyachok" was connected in Gubkin. In addition, "Belgorod Heat Grid Company" built heat grids to the perinatal center which is under construction in the city of Belgorod.

Connection to the central heating system is carried out at the expense of connected consumers, according to the connection tariffs established by the Commission for the State Regulation of Prices and Tariffs in the Belgorod Region. After putting new facilities into operation, energy supply contracts are entered into with JSC "Belgorod Heat Grid Company".

In 2015, the company will continue works on grids connection of new consumers to heat grids.