Stroytransgaz Commissioned First Unit at Yugo-Zapadnaya Plant
OREANDA-NEWS. August 12, 2011. At the first phase of the Yugo-Zapadnaya cogeneration plant construction, where Stroytransgaz is a general contractor, the First Unit was connected to the city’s power grid.
At present the final stage of commissioning is under way, the gas-turbine unit is switched to the idle running, and the steam turbine is being connected.
Additional information:
The Yugo-Zapadnaya cogeneration plant is a project of great importance. It is carried out within the framework of upgrading energy generation for
In 2007 Stroytransgaz and Yugo-Zapadnaya TEC JSC concluded a general contract for the construction of the Yugo-Zapadnaya cogeneration plant. As per the contract, the scope of Stroytransgaz includes construction, installation, and commissioning, engineering survey, the development of project documentation, and equipment and material delivery.
The execution of the project with the total installed electric capacity of 570 MW and heating energy capacity of 660 Gcal/hour provides for two startup phases. The first phase of the cogeneration plant of 200 MW of electric capacity and 255 Gcal/hour of heating energy capacity is expected to be commissioned in 2011. The second phase will be completed in 2014.